CAESS benefits over 120 families with an investment of $ 38 000


On Saturday 6 November, the Lotificación El Sauce 1 Soyapango was benefited by the removal of old lines representing private a danger to the community. This as part Standardization Plan for Third Party CAESS, contributing to those communities that have irregularities in their electrical installations.

These new lines have been built under standard rules SIGET and includes the installation of 38 new poles of different heights, over 5 kms length of medium and low voltage, the change of 120 rush low voltage and installation of 3 new transformers.

All this effort made by CAESS, represented an investment of $ 38,340.05 U.S. dollars, benefiting about 560 people in the community that now have better and more secure electrical service.